Project C.A.P.S. Inc.

Bridgeton, Missouri
Role: General Contractor
Project Highlights:

– 28,000 SF Warehouse Addition

– Tilt-up Construction

– Site carved out of a hill – mass excavation.

– Retaining wall 800 LF 15′ peak elevation and retention basin.

-Rebuild of site infrastructure including the gas service, electric service, storm and sanitary sewer, water.

– Half docks down at a time so that the exsting manufacturing plant was fully operational

– 7 new loading docks. dock drive and parking lot.